Attenuating Mass Concrete Effects in Drilled Shafts

FDOT Project #BD-544-39


Voided Shaft Construction WebCam Archives

  • 7:30-9:00am Setup / Excavation


  • 9-10:00am Excavation / Clean-out


  • 10-11:00am Clean-out / Settle / Final Clean-out


  • 11-12:00pm Cage Placement


  • 12-1:00pm Central Casing Placement / Concreting


  • 1-2:00pm Concreting / Surface Casing Removal


  • 2-3:00pm Clean up / Instrumentation


  • 3-4:00pm Instrumentation